Timesheet to Task Actuals Sync

Description

This feature allows Approved Timesheet hours against Projects to be calculated and applied as Actuals in the Altus Project Task schedule.

The Timesheet to Task Actuals sync feature is only available if Timesheets are in 'Project Tasks' Mode. If the Timesheets for an environment are set to 'Projects' Mode then this feature will not display.

This feature is only relevant to Projects whose schedules are native to Altus - it is not enabled for externally synchronised Projects.

Configuration settings

Image shows the Timesheet configuration screen

  • Display Name: Timesheets
  • Name: timesheetConfiguration

Relevant Fields:

  • Timesheet Mode: must be set to 'Project Tasks' for the feature to be turned available (and for the Allow Timesheet Actuals to Task Sync toggle to display)
  • Allow Timesheet Actuals to Task Sync: Must be set to 'Yes' for the feature to be available